Traffic Calming Rose Park Kill Lane

Type: Motion
Status: Open
Cllr Thomas Joseph raised a motion requesting the installation of appropriate traffic-calming measures at Rose Park and the surrounding roads adjoining Kill Avenue (details supplied) to address ongoing safety concerns. The motion highlighted the risks posed to the many older residents and children living in the estate by vehicles travelling at excessive speeds and using the area as a shortcut through the wider road network. It also requested a report outlining the proposed actions and implementation timeline to be presented to the Area Committee at its next meeting.
Recent Update:
Report Presented in Council ICC meeting 28th October - with recommendations below. Detailed report attached
Recommendation
1. Consider the introduction of additional traffic calming measures within the area
to address speeding concerns.
2. No specific measures are recommended in relation to rat running at this time, as
the available data does not indicate a significant issue.
3. Progress the assessment and design of a pedestrian crossing facility at the Kill
Avenue / Birch Grove junction.
-----------------------------------------
Motion passed and waiting for site vist--
Site Visit on Thursday 13th August 2026 at 4.45PM at Rose Park (near 43 Rose Park). Any change will be updated here.
13/08/2026 : Site visit conducted with residents. The Council needs to consider safety concerns at the Rose Park bend and at two locations on Kill Avenue (bypass): the road opening from Rose Park, and particularly the road opening from Birch Grove.
17/08/2026 : Raised ticket seeking an update on the status of large excavations in Kill Ave and highlighting safety concerns, requesting that additional safety measures be considered to protect children and other members of the public using the area.
Report Presented in Council ICC meeting 28th October - with recommendations below. Detailed report attached
Recommendation
1. Consider the introduction of additional traffic calming measures within the area
to address speeding concerns.
2. No specific measures are recommended in relation to rat running at this time, as
the available data does not indicate a significant issue.
3. Progress the assessment and design of a pedestrian crossing facility at the Kill
Avenue / Birch Grove junction.
-----------------------------------------
Motion passed and waiting for site vist--
Site Visit on Thursday 13th August 2026 at 4.45PM at Rose Park (near 43 Rose Park). Any change will be updated here.
13/08/2026 : Site visit conducted with residents. The Council needs to consider safety concerns at the Rose Park bend and at two locations on Kill Avenue (bypass): the road opening from Rose Park, and particularly the road opening from Birch Grove.
17/08/2026 : Raised ticket seeking an update on the status of large excavations in Kill Ave and highlighting safety concerns, requesting that additional safety measures be considered to protect children and other members of the public using the area.
Date:
Start Date: 02/06/2026 Status Date: 04/09/2026