Road Repair Meadow Vale, Deansgrange

Type: Motion
Status: Open
Cllr Thomas Joseph raised a motion requesting arrangements to replace bitumen in the road joints, repair instances of subsidence, and carry out repairs to the road surface on Meadow Vale, Deansgrange. This motion passed, and the response included the following: "An inspection was recently carried out. The road is in fair condition, with cracks found in isolated locations with missing or old bitumen in the road joints. Considering its condition, it is proposed to include the road on the next Sustainable Patching Programme for completion this year, which will entail repairs to the isolated locations as necessary."
Recent Update:
From: Agenda Meetings (GP)
Sent: Thursday 15 October 2026 11:19
To: Thomas Joseph
Subject: Re: Road Repairs on Meadow Vale, Deansgrange
CAUTION: [EXTERNAL EMAIL] Do not click links or attachments unless you recognise the sender and know the content is safe.
Dear Councillor Joseph,
Our Road Maintenance Section have issued the following response on the matter.
Road Maintenance are currently getting quotes for the works on the planters. We’ll have to review the cost of this before we can commit to whether it will be completed this year or not.
In terms of the road resurfacing, Meadow Vale, Deansgrange won’t be put on a programme, based on its current condition versus other roads in the county which need to be addressed as a priority.
-----------------------------
From: Thomas Joseph
Sent: Monday 12 October 2026 19:17
To: Agenda Meetings (GP)
Subject: Road Repairs on Meadow Vale, Deansgrange
Hi,
I am writing to follow up on the motion regarding road repairs on Meadow Vale, Deansgrange, raised at the Dún Laoghaire Area Committee meeting on 24 February 2025.
The response indicated that the road would be included in the Sustainable Patching Programme. Could you please provide an update on the current status of the works and the anticipated timeframe for completion?
I look forward to hearing from you.
-------------------------------------------------
- In communication with Road works team. Email sent
1st August 2026
Monday 2 March 2026
Friday 27 February 2026
From: Agenda Meetings (GP)
Sent: Thursday 15 October 2026 11:19
To: Thomas Joseph
Subject: Re: Road Repairs on Meadow Vale, Deansgrange
CAUTION: [EXTERNAL EMAIL] Do not click links or attachments unless you recognise the sender and know the content is safe.
Dear Councillor Joseph,
Our Road Maintenance Section have issued the following response on the matter.
Road Maintenance are currently getting quotes for the works on the planters. We’ll have to review the cost of this before we can commit to whether it will be completed this year or not.
In terms of the road resurfacing, Meadow Vale, Deansgrange won’t be put on a programme, based on its current condition versus other roads in the county which need to be addressed as a priority.
-----------------------------
From: Thomas Joseph
Sent: Monday 12 October 2026 19:17
To: Agenda Meetings (GP)
Subject: Road Repairs on Meadow Vale, Deansgrange
Hi,
I am writing to follow up on the motion regarding road repairs on Meadow Vale, Deansgrange, raised at the Dún Laoghaire Area Committee meeting on 24 February 2025.
The response indicated that the road would be included in the Sustainable Patching Programme. Could you please provide an update on the current status of the works and the anticipated timeframe for completion?
I look forward to hearing from you.
-------------------------------------------------
- In communication with Road works team. Email sent
1st August 2026
Monday 2 March 2026
Friday 27 February 2026
Date:
Start Date: 24/02/2025 Status Date: 06/08/2026