Ulverton Road

Type: Motion
Status: Pending
Cllr Thomas Joseph made a motion on speed calming measures at Ulverton Road as below.
That the Chief Executive would arrange for a traffic and speed survey on Ulverton Road,Dalkey, particularly at the blind corner on the approach to Dalkey Village from Glasthule,where vehicles, including buses and heavy traffic, frequently travel at speed, posing a serious safety risk to pedestrians, and to assess appropriate traffic calming and safety measures, with
a report to be presented at the next Area Committee meeting.
The report concluded the following: "The Traffic and Road Safety Section will carry out a speed survey along Ulverston Road. The results of the survey will be presented to this committee at the June meeting."
TAG Report ICC 28th October 2026 DLR-CRM 407782
Recommended installing speed ramps and keeping the location under review. The Traffic Advisory Group (TAG) acknowledged the concerns raised regarding visibility and vehicle manoeuvrability for right-turn movements exiting Church Road onto Ulverton Road. As part of the development of the Ulverton Road traffic calming scheme, the original concept design included the introduction of double yellow lines in the vicinity of the Church Road junction, in conjunction with two proposed bus-friendly speed ramps near Ulverton Close. The proposed parking restrictions were intended to improve visibility and reduce potential conflict between turning and oncoming vehicles. However, during the consultation process, concerns were raised by local residents regarding the potential loss of on-street parking. Following consideration of these submissions, it was agreed to retain the existing parking provision at this stage. This decision was based on the expectation that the proposed bus-friendly speed ramps would significantly reduce vehicle speeds along this section of Ulverton Road, thereby mitigating the identified safety concerns without the immediate need for parking restrictions. Accordingly, TAG did not recommend progressing double yellow lines at this time. However, the location will continue to be monitored following implementation of the traffic calming measures. Should safety concerns persist, or evidence emerge that parked vehicles are creating an unacceptable hazard, the introduction of double yellow lines may be reconsidered in the future.
--------------------------------------------------------
10/09/2026
We propose the introduction of double yellow lines around the junction to prevent vehicle parking and improve visibility and safety.In addition, we have settled on the installation of two bus-friendly speed ramps on Ulverton Road, one to the north and one to the south of the junction.As the ramps must be located in accordance with the relevant standards and in conjunction with existing public lighting, we are currently confirming the most suitable locations.
Appropriate traffic signs associated with the speed ramps will also be provided.We are currently undertaking the topographical survey to support the detailed design.
09/09/2026
We have now secured NTA funding for the project and have discussed the proposed scheme at our TAG meeting, where no issues were raised. We are currently progressing the design and aim to deliver the improvements as quickly as possible and, if all goes to plan, have the works completed before November.
-----
13/08/2026 -Waitng for funding . Work submitted to the planning for extending double yellow line and two speed ramp 50-100m difference.
----
A site visit organised with DLR CC engineers and residents on 5th June 2026
-------
Note July 30 2026- The engineer who carried out the site visit proposed installing double yellow lines and a speed bump at the bend on Ulverton Road, where there is already a continuous white line. The double yellow lines must be approved by the Traffic Advisory Group (TAG). The speed bump, or other traffic calming measures, will be considered later this year or in early 2027.
-------
Date:
Start Date: 25/05/2026 Status Date: 01/10/2026